MAPS 3 Modern Streetcar Construction Update

Print

Streetcar Construction Continues

Updated: May 12, 2017

Stay updated on OKC Streetcar-related construction and traffic flow changes by signing up for email alerts.

 

 Joe Carter Avenue: May 15 - June 2

  • Two lanes of Joe Carter are open for northbound and southbound traffic.
  • Concrete work for the first platform will start once the conduit work in the alley is complete.

joecarter_040717

Reno Avenue: May 15 - May 19

  • The northernmost westbound lane on Reno between Joe Carter and Oklahoma Ave. will be closed for concrete work.

 reno_031017

reno_050517_2

Sheridan Avenue: May 15 - July 7

  • Road demolition will continue on Sheridan with track installation to follow.

 sheridan_050517_1sheridan_050517_2sheridan_050517_3

Sheridan Avenue: May 15 - May 19

  • The intersection of Sheridan and Mickey Mantle will be closed for road demolition.
  • It will be plated at the end of each day and will not be closed at the same time as Oklahoma.

Sheridan_051217_4 

Dewey Avenue: May 15 - May 26

  • Cimarron will continue the utility work on NW 10th Street between Walker and Hudson.
  •  Both the eastbound and westbound lanes will be completely closed,as will the on-street parking.

dewey_051217

Hudson Avenue: May 15 - May 31

  • The southern portion of Hudson closest to Sheridan, as well as this section of Sheridan, will be closed for storm and sanitary work.

hudson_050517_1

Hudson Avenue: May 15 - May 19

  • The portion of Hudson between SW 2nd Street and SW 3rd Street will be fully closed to conduct sanitary sewer work.

Hudson_032417

Hudson Avenue: May 15 - May 31

  • The portion of Hudson between SW 3rd Street and SW 7th Street will be fully closed to conduct road demolition and track installation.

hudson_033117_2

Harvey Avenue: May 15 - May 19

  • The portion of Harvey off of SW 3rd Street will be fully closed for road demolition and track installation.
  • The road can be plated and reopened nightly if needed for events during track construction.

harvey_033117

Robinson Avenue: May 15 - May 19

  • This portion of Robinson will go down to two lanes for utility work.

robinson_050517_1

Robinson Avenue: May 17 - May 31

  • Two-way traffic will be maintained on Robinson while utility work is being done in that area.

robinson_050517_2

ONG will continue their utility work on NW 9th Street, with NW 8th Street to follow.