Hudson between Main and Sheridan closed 11/13
Hudson between Main and Sheridan will close Sunday, November 13 from 6 a.m.
to 6 p.m. while crews perform a fire pump test.
Intersection of Lee and Couch reduced*
The intersection of Lee and Couch will be reduced to one south bound lane on
Lee and one west bound lane on Couch. North bound Lee will be detoured to
Shartel.
Park and Hudson Intersection closed 11/14 (6
p.m. – 5 a.m.)*
The intersection of Park and Hudson will close at 6 p.m. on November 14 and
reopen at 5 a.m. on November 15 so crews can connect a water line.
Broadway between Main and Sheridan closed
10/28 - 11/21*
Broadway between Main and Sheriden will close through November 21 so crews
can install a water line. Local access will be maintained.
American Motor Garage Pedestrian Access
Reduced*
A portion of the west sidewalk on Hudson will be closed. The closure is from
American Motor Garage north to the alley. Pedestrians can cross Hudson at
Sheridan or Main.
Intersection of McGee and Hudson reduced 11/11 – 11/12*
The intersection of McGee and Hudson will be reduced to two south bound
lanes after 9 a.m. on November 11 – November 12 while crews replace
pavement.
McGee between Walker and Hudson reduced*
McGee between Walker and Hudson will be reduced to one west bound lane and
one east bound lane so crews can replace pavement.
Sheridan between Broadway and Gaylord reduced*
Sheridan between Broadway and Gaylord will be reduced to one west bound lane
and two east bound lanes so crews can install a new water line.
Intersection of Robinson & NW4th reduced*
Intersection of Robinson & NW 4th will be reduced to one east bound lane on
and two west bound lanes on NW 4th while crews repair a manhole.
Intersection of Walker and Main*
Traffic is shifted to the west side of the intersection at Walker and Main.
The south crosswalk will be closed, all other crosswalks in the intersection
will be open.
South half of Sheridan closed from Walker to Hudson*
The south half of Sheridan from Walker to Hudson will be closed so crews can
remove the pavement and relocate utilities. There will be one westbound and
one eastbound lane of traffic.
Couch between Lee and Walker reduced*
Couch between Lee and Walker reduced to one westbound lane while utility
crews make relocations.
Century Center Parking Garage Pedestrian Access reduced*
A portion of the north sidewalk on Sheridan will be closed. The closure is
from Robinson east to the entrance of the parking garage. Pedestrians can
cross at Broadway and Sheridan. Pedestrian access to the garage will be from
the Robinson or Main entrances.
Sheridan Walker Parking Garage Pedestrian Access reduced*
A portion of the west sidewalk on Walker will be closed. The closure is from
Sheridan north to the entrance of the parking garage. Pedestrians can cross
Walker at Sheridan or use the north elevator at the garage and cross at Main
and Walker.
West half of Harvey closed from Park to the Devon garage entrance*
Crews will begin to remove pavement and relocate utilities on the west half
of Harvey from Park to the garage entrance.
West side of Walker from Colcord to McGee Closed*
The west side of Walker from Colcord to McGee will be closed for utility
relocations.
Robinson from Sheridan to Park closed*
Construction crews will begin pavement removal at the intersection of Main
and Robinson to allow for a new water line and utility relocation. Robinson
from Sheridan to Park is expected to be closed through November.
West side of Hudson closed from Reno to Couch*
The west side of Hudson is closed from Reno to Couch so construction crews
can remove pavement and work on the water line. Two south bound lanes of
traffic are open.
Sheridan between Hudson and Robinson closed until
2012*
Sheridan Avenue between Hudson Avenue and Robinson Avenue remains
closed for renovation on the Myriad Botanical Gardens and private downtown
renovations.
All project timelines are
contingent upon the weather.
*Denotes Project 180-related construction.
Contact:
Shannon Cox, 297-2130